Jan 11, 2011 LMS meeting

At the Jan 11, 2011 LMS meeting, the timeline for pilot Phase II was confirmed:

  • Spring/Summer/Fall 2011: expand Bb 9.1 pilot to include additional instructors
  • Spring/Summer 2011: expand pilot to include other LMS options (CanvasMoodle and Sakai) along with Bb 9.1 .
  • Fall 2011: expand pilot testing – include all 4 LMS’s and have them tested by as many pilot testers as are available and is feasible.
  • Fall 2011: Collect data, conduct analysis, select LMS option(s) to test on campus