SDC Pool Update

We are excited to announce that the SDC lap pool re-opens today, Monday, January 20! The dive tank remains closed at this time.

Lap swim and open swim hours have been updated for the spring semester. NOTE: There will be NO adult lap swim Monday-Friday, 11:30am-1:30pm. We currently do not have available lifeguard staff to cover this shift.

Updated SDC Building Schedule

Phase 1 Pool Renovation Update

We are pleased to announce that during the first stage of renovation, December 13, 2019 – January 19, 2020, the following list of items have been addressed:

  • Dive tank was acid washed and gutters were regrouted and cleaned.
  • Wall and bench tiles were replaced/repaired.
  • Pool deck tiles were replaced/repaired.
  • Bleachers were removed.

Phase 2 Pool Renovation Tentative Schedule (to be completed in April/May 2020)

  • Replace filtration system.
  • Venting of mechanical room.
  • Acid washing of lap pool.
  • Removal of platform and removal/replacement of dive boards.
  • Replacement of bleachers.

Thank you for your patience as we continue to work through the renovation project. We look forward to seeing you at the pool!


Comments Closed